Case Study: EV Infrastructure & Civil Works Deployment in Mackay, QLD

Case Study: EV Infrastructure & Civil Works Deployment in Mackay, QLD

Client: Addelec
Location: Mackay, QLD
Budget: Not disclosed
Date: May/June 2025

Services Provided:

  • Civil Works
  • Underground Reticulation
  • Switch Board Installation
  • EV Charger Installation
  • Power and Data Installation and Termination
  • Street Lighting

Project Overview

Addelec engaged our team to deliver a full-scale infrastructure installation in Mackay, QLD, focused on deploying ABB EV charging systems and supporting electrical upgrades. The scope of work included:

  • Installation of a new 400A Main Switch Board with 240mm 3-phase cabling
  • Underground power supply to two ABB Terra 184 DC Fast Chargers using 185mm 3-phase cabling
  • Installation of 2 x ABB Terra 184 DC Fast Chargers
  • Installation of a 6-meter streetlight with PE cell
  • CCTV setup featuring a 270° fisheye camera
  • Data network installation and termination using Cat6a shielded cabling
  • All trenching works
  • Installation of Concrete foundations for chargers, Main Switch Board, and streetlight
  • Backfill and compaction of trenches
  • Reinstallation of asphalt
  • Installation of topsoil and Grass seed
  • Line marking of the site
  • Temporary fencing and waste disposal for the site

Challenges & Solutions

Challenge

Solution

Site located 881km from our home office, requiring complex logistics

Coordinated delivery schedules with Addelec and mobilized tools and equipment efficiently to and from site

Car park needed to remain operational during construction

Implemented staged work zones and clear signage to ensure uninterrupted access

Coordination with DNSP (Ergon) for power integration

Scheduled DNSP activities in advance and maintained proactive communication

Multi-party communication between our team, Addelec, and NRMA

Established centralized communication protocols and held regular check-ins to ensure alignment

Outcome

The project was delivered on time and met all technical and operational requirements. The infrastructure now supports high-speed EV charging, enhanced lighting and surveillance, and robust data connectivity. The car park remained functional throughout the build, and all stakeholders were kept informed and engaged.

Client Benefit

The upgraded site offers improved safety, modern amenities, and future-ready EV infrastructure. Seamless coordination and execution ensured minimal disruption and maximum value for Addelec and the end customer, NRMA.

Additional Information

Photos from the site showcase the quality and precision of the completed work. This successful deployment sets a benchmark for future regional infrastructure projects.

EV Charging

Tagline

Efficient, future-ready infrastructure delivered with precision—881km from home base, zero compromise on quality.

 

Share Post