Terawatt has partnered with Brighte to offer 0% Interest Payment Plans for EV Chargers. Learn More

Case Study: EV Infrastructure & Civil Works Deployment in Morven, QLD

Client: Addelec
Location: Morven Roadhouse, QLD
Budget: Not disclosed
Date: December 2024

Services Provided:

  • Civil Works
  • Underground Reticulation
  • Switch Board Installations
  • EV Charger Installation
  • Power and Data Installation and Termination
  • New Property Pole + Removal of Obsolete Pole

Project Overview

Addelec engaged our team to deliver a full-scale infrastructure installation at the Morven Roadhouse, QLD, focused on deploying ABB EV charging systems and supporting electrical upgrades. The scope of work included:

  • Installation of a new 300A Main Switch Board for both the Roadhouse and the new EV charger infrastructure
  • New underground mains supply from Ergon via a newly installed property pole
  • Underground power supply to one eLumina 200kW charger (with inbuilt battery) and one ABB 22kW AC charger
  • Installation of both chargers
  • Installation of lighting with PE cell on a 6-meter street pole
  • CCTV setup featuring a 270° fisheye camera
  • Data network installation and termination using Cat6a shielded cabling
  • All trenching works
  • Supply and installation of a new electrical property pole
  • Concrete foundations for chargers and MSB
  • Supply and installation of a new concrete parking slab (15m x 5.4m x 0.2m)
  • Backfill and compaction of trenches
  • Line marking of the site
  • Temporary fencing and waste disposal for the site

Challenges & Solutions

Challenge

Solution

Site located 711km from our home office, requiring complex logistics

Coordinated delivery schedules with Addelec and mobilized tools and equipment efficiently to and from site

Original installation location was obstructed by a newly built parking slab and toilet block

Communicated with the site owner and Addelec to propose and gain approval for an alternative location, allowing the project to proceed without delay

Roadhouse shared the same power supply and needed to remain operational

Implemented staged work zones, clear signage, and arranged a backup generator to maintain power during changeover

Trenching crossed a path used by large cattle road trains

Engaged a civil expert to manage digging and re-compaction to prevent slumping

Coordination with DNSP (Ergon) for power integration

Scheduled activities in advance and maintained proactive communication

DNSP raised issues with CT metering and connection requirements, causing delays

Invested additional time and made multiple return trips to resolve concerns and ensure compliance, leading to successful CT metering connection

Limited power supply from DNSP (only 50A additional available)

Addelec supplied an eLumina 200kW battery-integrated EV fast charger, capable of delivering 204kW charging with just 10–40kW input

Outcome

The project was delivered on time, with the exception of a partial delay related to DNSP approvals for the chargers. All technical and operational requirements were met. The infrastructure now supports high-speed EV charging, enhanced lighting and surveillance, and robust data connectivity. The Roadhouse remained functional throughout the build, with only a planned 4-hour shutdown.

Client Benefit

The upgraded site offers improved safety, modern amenities, and future-ready EV infrastructure. Seamless coordination and execution ensured minimal disruption and maximum value for Addelec and the end customer, NRMA.

Additional Information

Photos from the site showcase the quality and precision of the completed work. This successful deployment sets a benchmark for future regional infrastructure projects.

EV charger installation Morven

EV charger installation Morven

 

EV charger installation Morven

Tagline

Efficient, future-ready infrastructure delivered with precision—711km from home base, zero compromise on quality.

Share Post

Related Posts